SFCSS building works update

 

KOTA KINABALU – About 63 percent of the St Francis Convent Secondary School building project has been completed at the end of January 2017.

A spokesperson for the building committee said this on 27 Feb 2017.

She also said that a balance of over RM2m is still required to complete the RM12m building project comprising four-storey two parallel blocks with 22 classrooms, living skills workshops, science labs, offices, staff room, library and special rooms.

Started in 2015, the project is scheduled for completion in June 2018.

The spokesperson expressed the hope that generous alumni members (especially those who have already pledged but not yet contributed), benefactors and well-wishers will come forward to help complete the project.